Building Straw Bale Walls

Building with straw bales is a relatively recent concept in Ireland. Most buildings were constructed within the last two decades, representing a tiny proportion of all homes, but, in many ways,  ideally suited to the novice self-builder.

There are many reasons to build with straw; low environmental impact, cheap and locally available, excellent insulation and breathable properties, providing a very healthy living environment (see a summary by Andrew Morrison at Strawbale.com). As  beginners we found Barbara Jones’ book indispensable. We also attended some courses run by Straw Works in the UK before returning to Ireland.

Construction of our non-load bearing walls was reasonably straightforward requiring a minimum of tools. However, there was preparation work to be completed before we began to build our wall. Similarly, when we had built our walls, we needed to work on the space between the top of the walls and the underside of the roof – the void – we called it!

1) Wooden ring beam/plinth: we built the ring beam in May 2017 after we finished debarking our roundwood. The beams consist of 300mm x 50mm (12″ x 2″) C24 timber with OSB (18mm) on the top and bottom. It’s important to use long lengths – as the ring beam will bear the weight of the bales, doors, windows and floors – so it needs to be very strong. The completed ring beam sits on top of the filled car tyres, we also placed damp proof course (DPC) and marine ply to meet regulations and to reduce the possibility of any water ingress.

The other main function of the ring beam is to provide a raised plinth to protect the straw bales from water splashing upwards during periods of rainfall. Externally, the ring beam will be covered with lime plaster.

 

P1100960
Wooden ring beams laid on top of the car-tyre foundation

The ring beams were stored until we began to install them in January ’19. We insulated the beams and covered them with OSB. We also added lengths of 100mm x 44mm (4″ x 2″) timber on top of the OSB to further strengthen the beam and to support the door and window openings and house the hazel stubs. The spaces between the timber were filled with Leca which acts as a moisture soak in the event of any water getting into the straw.

Fixing posts for windows and doors were added at this time. These posts consisted of 2 x (2 x 100mm x 44mm) (4″ x 2″) nailed together and fixed to the ring beam at the bottom and the wooden frame fixed to the roof rafters at the top. We needed to change some of our original window locations and sizes to accommodate the wooden braces in our main structure.

IMAG0172
Jal testing the warmth of our insulation
IMAG0175
Working on the ring beam

 

2) The First Bale

We began building our walls in mid-February. Our bale plan is based on an average bale size of 1m (40″). However, it is impossible to produce bales to a single length, so bales have to be re-sized and cut for window and door frames. It’s important in the early stages of building with straw to take things slowly and carefully.

The first course was secured in place by hazel stubs and as our walls rose to the fourth course we pinned them with longer (1m / 40″ hazel sticks at two per bale). Before pinning we checked the walls for straightness.

IMAG0227
Pinning the first four courses beside a fixing post for a  windows.
P1120471
Hazel stubs in place for the first course of bales. LECA added as protection against moisture.

 

 

 

3) Compressing the walls

By mid April we were up to the sixth course of bales. As our walls are not load-bearing we had to come up with a solution to filling the space between the top of the wall and the ceiling. We did this by building a wallplate panel using  100mm x 44mm (4″ x 2″) timber and OSB. We suspended this from the roof rafters to allow for the seventh course to be put in place. We then compressed the walls with ratchet straps and sealed the compression with polystyrene straps (purchased from BM Packaging). The ratchet straps were placed under the ring beam and over the wallplate panel which meant that we were able to spread the compressive forces equally along the wall.

Compression  has a transformative effect on the walls, giving them much greater solidity and stability. We gained an average compression of 100mm (in seven bales). For windows and doors we did some test compression so that we could place lintels correctly. If they were too high or low they would affect the compression. When satisfied with the walls we gave them a hair cut to remove all the loose straw.

IMAG0039
Wallplate panel suspended above the walls before compression.
P1120597
Walls compressed using ratchet straps
IMAG0052.jpg
Trimming the loose straw before compressing the walls

 

Before we completed the work on the walls we had to build our porch, as it wasn’t part of the main roundwood structure and would be load-bearing. We had to wait for some dry weather as we reckoned it would take two weeks or so to build the porch and its roof.

Unfortunately, during the building of the porch we suffered a leak and had to rebuild part of the wall – one of the disadvantages of building without a roof overhead.

We completed the porch and roof  in mid-June and were now in a position to begin the focus on insulating and water-proofing the roof.

 

P1120608.JPG
Building the porch roof
P1120575
Straw bale walls can be built with simple tools

 

 

 

 

 

 

 

 

Additional jobs: Earth Anchors

We installed earth anchors so that our structure is correctly anchored into the ground. Despite our structures strength it could be susceptible to uplift in stormy weather, with wind acting on the 500 mm roof overhang which extends around the perimeter.

The anchors are driven about 2m (6ft) into the ground and the stainless steel lanyard is then jacked up with a tractor jack to apply the correct force and ensure that the anchor is properly employed. The lanyard will be eventually connected to the posts to prevent uplift. We were grateful to Osian for helping us install these and to Bobby Bazelgette from Solarwheel who advised and supplied the earth anchors.

P1120616
Using a tractor jack to apply 2.5 tonnes of pressure on the anchor to ensure it opens and is correctly installed
P1120611
Installing earth anchors with a jack hammer (with a special applicator tool)

 

 

 

 

 

 

 

 

 

 

The next task is to insulate and waterproof the roof and then begin preparing for plastering the exterior walls. We hope to be able to move inside in the winter months to begin work on the interior.

P1120636.JPG
Living roof in bloom
P1120633
The wildflower roof on our workshop in Summer

 

 

 

 

Building the Roof (II)

Summer 2018 was a record-breaking season with the warmest and sunniest weather in over 40 years. Such exceptional weather was ideal for building a 200 sq m roof as we were working under the sky for the entire summer. The overhang (500 mm) adds a lot of extra area to the roof – the overhang being necessary to protect the walls from driving rain. We had already covered a lot of the roof with cladding and now needed to build the roof deck to support the insulation and the living roof.

Part 1: Roof deck

The roof deck involved fixing square timber to round timber, which added a level of complexity and difficulty to the task. The first layer of the deck consisted of 150 mm x 50 mm (6″x 2″) timber laid over, and in opposition to, the roundwood rafters at 400 mm centres, where possible (for greater span we used some 220 mm x 50 mm).

Building the deck on the L-shaped part of the roof (north and east side) was reasonably straightforward as the surfaces were quite even and only slightly sloping. However for the reciprocal roofs, it was a very difficult and time consuming task, as the roof surface is made up of many different planes which needed be connected and covered. The complexity of this task considerably lengthened the time budget for the roof. We once again engaged Osian to help us with the carpentry on the roof and to speed up the process. The roof deck took 16 weeks to complete.

IMG-20180627-WA0001
The north-east corner of the roof
P1120140
Larch cladding on the roof. This is also the internal finish on the ceiling.

 

Each reciprocal roof required over 100 separate and different pieces of OSB to cover it – like solving a big wooden jigsaw puzzle. Each piece had to be individually measured, cut, offered up, altered, glued and nailed.

 

P1120272
Detail of completed OSB deck on the south side of the roof.
P1120157
Detail of the 150 mm x 50 mm deck

 

Timber size and strength dictates the span it can be used for (see span tables). An alternative approach for our roof could have been to use larger timber e.g. 225 mm x 50 mm (9″ x 2″) to enable greater spans to be achieved, and would have used slightly less timber. However, the complexity of covering the reciprocal parts of the roof would remain. Another alternative would have been to make up grillages on the ground to cover this part of the roof and use a crane to lift them into place (a more expensive option).

 

P1120222
Lots and lots of measuring, cutting, nailing, gluing, offering up…at least it was sunny 🙂
P1120239
View of the east side of the house

 

 

Part 2: Fascia

The purpose of the fascia is to cover and protect the roof’s supporting timbers and insulation. Due to the size of our roof rafters and the deck we built, the height of the fascia in places is almost 1,000 mm. It also follows the contours of the roof, so that it is wavy in appearance.

For most of the roof, the fascia consists of 3 lengths of 225 mm x 20 mm fascia board which is biscuit-jointed, glued, and screwed together. It was then nailed on to the roof. The fascia was built in various sections, which were then fitted together onto the roof. This work took place at the beginning of September. The weather was still good for roofing and we were hoping to complete our roof covering before the weather changed.

 

P1120288
Fascia following the roofs shape
P1120283
Osian helping us out to build the fascia

 

Part 3: Vapour Barrier

The purpose of the vapour barrier is to prevent the build up of moisture in the roof’s structure when cold and warm air meet. We contacted Laydex who supply systems for green roofs. The Vapour Barrier we used was Alutrix 600, which is a high performance barrier. Applying this was straightforward, a primer was painted on and then the Alutrix was applied (there are excellent videos to help do this).

P1120335
Applying primer
P1120341
Vapour Barrier on roof lean-to

 

The completed roof…

IMG-20181005-WA0001

 

Part 4: Roof Lights

During the building of the deck, Osian made four wooden dodecagons (12-sided shaped) which were affixed to the roof openings, once the rafters were cut back and levelled. We recycled some of the Larch we had kept from our framing bed for this.

 

P1120173
One of the four larch dodecagons for the roof opening
P1120167
Larch dodecagon in place

 

We purchased two roof lights online and they were relatively easy to install, although this depended on the weather. As it was now November, we had to wait for a calm, dry day to complete the installation.

 

P1120416
Roof light installed
P1120415
Roof kerb in place

 

Unfortunately, time and the weather were against completing the roof in 2018. It still needs to be insulated and covered with the waterproof barrier. We were a bit disappointed because ideally the roof should have been water-proof by the end of the year. It may well be that our time scales were over-ambitious as there is a high level of unforeseen complexity to the work, which, as amateurs, we found difficult to factor in.

Towards the end of 2018, we covered the entire roof with 1000-gauge polythene to protect the vapour barrier. We will be aiming to complete the roof in 2019, with perhaps a more realisable timescale.

Building the Roof (I)

Building in Winter was a real test of stamina and strength. Building in late Spring and early Summer has been, in contrast, joyful. The site has been transformed by the rush of new growth. Birds building nests or searching for food, the cows basking in the glorious May sunshine with bellies full of grass. New wildflowers appear on a weekly basis, adding additional colours to the landscape. The season has also seen a prolonged period of fine, sunny, warm weather, a welcome break from the epic Winter we’ve endured, and ideal weather for roofing.

Following on from our roof-raising, we have been working on completing the rest of the roof structure. It consists of several main layers: 1) principle and common rafters; 2) waney-edged cladding/sarking boards; 3) decking, made from 6″ x 2″s and OSB; 4) insulation; 5) waterproof layer; and, lastly; soil.

The first layer was completed towards the end of April. This involved ensuring that everything was fixed properly and soundly, as the roof structure needs to be able to support its load. It has to be fixed so that any shear forces are directed downwards, or contained. The majority of the fixings were M20 high-tensile threaded bar and M20/M15 galvanised coach screws (300mm).

P1120019 (1)
The roof valley with the Slieve Bloom Mountains in the distance (May 2018)
P1110983
Fixing the secondary rafters onto the hip rafter (April 2018)

 

When we completed this layer, we said goodbye to Osian, our carpenter and friend, who helped us to realise our dream.DSC_0115

He has been superb in the quality of his work and also in his dedication to completing the structure through one of the longest and coldest winters in recent memory.

 

 

We began our second layer, which was to cover the entire roof with waney-edged cladding/sarking boards, in late April. We started on the easier part – the lean-to – rather than the reciprocal parts. We purchased a cordless drill and a circular saw to speed up the process. Holes needed to be pre-bored for the nails, as the timber is quite green and is likely to shrink over time, possibly resulting in splitting. The circular saw was essential as there are several thousand cuts to be made during the construction of this layer!

Luckily, the weather has really picked up and we have rarely been interrupted by adverse conditions. Ideal conditions for roofing.

 

P1120082 (1)
Cladding completed May 2018
P1120074
Ideal weather for roofing May 2018

 

Cladding the reciprocal roofs was quite challenging, as all boards have to be placed in a certain way so that from the inside, it should be appealing to the eye. Each board has to be individually measured and cut, drilled and nailed. Each reciprocal roof needed about 700 boards. A further issue with cladding the reciprocal roofs is that, because we have round wood rafters, it is not always possible for each rafter to be on the same plane so that some corners of the boards will stick up. However, this may only be a problem on the top of the roof; from the inside it will look fine.

WhatsApp Image 2018-06-11 at 16.26.29
Reciprocal roof – view from inside

Our next phase will be to complete the additional layers of the roof and the circular openings. When this is completed, we will have a waterproof roof and we can begin building our straw-bale walls.

Our timeline to achieve all of this is quite challenging as, ideally, we would like to complete our walls by early to mid-September – they need to be plastered before the Autumnal frosts begin.

Raising the Roof

We are now one year into the build. We’ve reached a significant milestone in that we  have now finished the bulk of the work on the main roundwood structure. This has taken the best part of six months. We are delighted with the outcome and are very thankful to Osian, our carpenter, for his skills and attention to detail, and to David and Chris for their engineering advice and opinions. We have a beautiful, unique and incredibly strong structure for our house.

P1110915
…to this! (Feb ’18)
P1100508
From this (Feb ’17) ….

 

Our work on the large roundwood poles has involved a huge effort. We’ve been working outdoors throughout the winter and have a new-found respect for builders, farmers and other workers who have to brave the elements in their daily endeavours! Working in sub-zero temperatures is tough and can be physically draining. Stamina, as well as creativity is a vital quality for a self builder, you just have to keep at it until you are satisfied (see video of the frame being erected here)

 

P1110793
Using chain-blocks to position each brace into place
P1110804
Misty, damp, cold morning

 

 

 

 

 

 

 

 

Raising the roof involved placing the two reciprocal roofs we built last year onto their resting place along the wall plate (beams). Great skill was needed, not only in building the reciprocal roofs, but also in constructing the posts and beams to accommodate them accurately. Ill-fitting beams and rafters would  compromise the strength of the structure. Osian’s attention to detail, and his carpentry skills, meant that we were very confident that everything would be fine. Ultimately each roof fit snugly and correctly into place.  It’s important in this type of construction to avoid tension in the joints and connections, as too much tension would eventually cause problems.

 

P1110825 (1)
Timber Engineering: Three beams meet at this junction. They are connected with M20 threaded bars and the trough is then filled with Rotafix TG6 Grout.
P1110869
Detail of one of the corner posts with beams and braces.

 

 

 

 

We contacted O’Grady Crane Hire to assist us with this lift, as each roof weighs about 2 tonnes and mechanical lifting was the only way to do this safely. We also needed to lift into place our largest rafter (600 kgs) which rests on the north-east corner of the lean-to and supports the joining of the north and east roofs. Some of our friends and family attended our Crane Day, and it was great to share this exciting day with all of them. The topping-out ceremony was completed by fixing some sprigs of Douglas Fir and Larch to the roof and adding some Holly (to symbolise longevity), completed by sprinkling some whiskey and a song in Welsh by Osian!

 

DSC_0135
…lands perfectly in place
DSC_0122
Reciprocal Roof lift, and it…

 

P1110915
The completed structure

 

Luckily, we were able to complete the work with the crane on that day because by the following week Storm Emma had caused the countryside to grind to a halt for several days.

Our next stage is to complete some of the remaining work on the frame, organise our scaffolding and begin work on adding the various layers to the roof. With straw bale building in a temperate climate, it’s vital to have a covering before you begin building the walls so as to protect the straw bales from absorbing excess moisture.

 

 

Assembling the Frame

Over the last month, we have begun to assemble the frame, which will support our roof. This process involves three distinct phases, 1) Initial working on roundwood, 2) Laying-up – checking the individual members (posts, braces, beams) fit together. This takes place on the ground, ideally on a level surface, and, 3) Erection of the frame – this usually involves erecting individual bents (post and beams joined together and braced) and joining them to each other with connecting beams or rafters. These processes take time and need  great skill and accuracy to achieve a strong structure. We have completed most of the first and second phases, although each phase will run until the end of the entire process.

Assembling the frame brings with it a great sense of achievement and, having spent the last four months working on the ground, it allows the structure to express its three-dimensional shape. It also allows us to begin to understand how our home will relate to its site and its environment.

 

P1110584
Erecting sections of the frame using a tripod and scaffolding

We were able to erect parts of the frame with our tripod and winch system (see video). However, for the large reciprocal roofs and beams, we decided that hiring a crane would be the most efficient and cost effective method of erecting the frame. Mechanical handling of the wood means is unavoidable given its size and the demands of safety.

Another important factor was the time it would take to dismantle and re-assemble the reciprocal roofs at height.

 

P1110596
A section or bent of the east frame being lifted into place

We contacted O’Gradys, a local crane hire firm to advise us on raising some of the structure. Our plans were interrupted by Hurricane Ophelia and Storm Brian (as cranes are not tolerant of wind speeds over 40-50km/hr) but eventually the weather settled and on a bright sunny morning our crane arrived! (see video)

Erecting the frame was an exciting experience for all involved. Working with a crane enables large heavy structures to be moved quickly and smoothly around the site. It is very satisfying to witness the bents we’ve been working on being lifted and slotted into place producing a really strong structure.

 

We envisage working with a crane on two subsequent days to fully complete the structure.

P1110570
Charring the bottom of the post to improve its resistance to moisture
P1110560
Pumping Rotafix Structural Adhesive (RSA), a strong resin which bonds the threaded bar to the wood.
P1110637
The east and north sides of the frame
P1110622
Drilling through the brace and the post to accommodate the M20 threaded bar which secures the structure

Building a Reciprocal Roof

A reciprocal roof is type of roof where the individual rafters mutually support each other. They originated in medieval Japan but probably date back further and aspects of reciprocity can be found in the roofs of many early human settlements. Reciprocal roofs are generally found on round, elliptical or polygonal buildings as the weight of the roof can be easily directed downwards via the post and beam henge on which it sits.

P1110268
The first rafter is held in supported by the upright charley stick. This is removed when the last rafter is in place allowing the roof to settle into its pitch.
P1110273
Osian scribing the beam onto the principle rafter to achieve a perfect fit.

 

 

 

 

 

 

 

 

 

 

We came across the idea and fell in love with this form of roof when we worked with Neil at Earthmovesdesign. When we were designing our house design we decided to incorporate a twin reciprocal roof over our open-plan kitchen and living room to divide the space and to draw light into it via the openings in the roof.

P1110278
Checking the angle of the scallop. With 12 principle rafters the angle at which they cross each other is 30 degrees.
P1110297
Using the tripod and winch to lower one of the principle rafters into place.

 

Our design did present a number of engineering problems. The first issue was how to build such a roof on a non-circular henge. We were advised by a specialist engineer, Chris Southgate, to add additional braces at each corner of the henge to deal with the weight of the roof.

P1110321
Beautifully executed seat cuts.
P1110363
Using a plum line to check that the opening maintains circularity. Each opening is 1 metre in diameter.

The other issue was how to set the roof pitch. Normally the rafters are laid on top of each other in the centre and the pitch is determined by their collective spiral height (= diameter of all rafters at their thinner end). Our spiral height would be between 2.5 and 3 metres which would produce a 45 degree pitch. However as our pitch was set for 30 degrees we had to scribe and scallop out the rafters to achieve this. Having a carpenter on board who was able to deal with the complexity of this design was essential.

P1110398
View from the top of the roof.
P1110403
View from the inside.

 

The task was very physically demanding as our rafters have a minimum diameter of 200mm and are up to 6m long. We used Tirfor winch and a 4 metre tripod which a local engineering firm, Coughlan Engineering, fabricated for us to lift the rafters into place. We built both roofs on the beams they will be affixed to on the ground, as assembling this at height would be very expensive. We aim to lift of each completed roof and lower it onto the henge when it is erected using a crane. (see construction video)

We were delighted with the finished result which is sculptural and beautiful.  We really look forward to gazing at the sky and the stars though our roof.

The next task is to lay-up the north and east post, beams and braces. We will then begin the process of erecting and fixing the frame and roof, which will take 4/5 weeks. We are hopeful of covering the structure before Winter so that we can complete some of the internal jobs before next Spring.

Working with Roundwood

In the last month we have been working alongside Osian Denman – a heritage carpenter – who has taken on the task of helping us to construct the roundwood frame and roof. This part of our build requires great expertise and skills to realise our design and to guarantee an excellent finish.

P1110229
Enjoying the weather and the woodwork

We are learning lots of new skills and are using an array of both traditional and modern tools. We’re enjoying learning about how the structure will all fit together.

We have been taking advantage of the long evenings where possible to pack in as much work as we can.

An essential characteristic of working with roundwood is to see both its roundness and the square inside at the same time. Roundwood carpentry is different from other woodwork in that the wood being used is in its natural state. Despite this it still relies on keeping things square and plum as in ‘normal’ carpentry.

P1110131
Using a plane to make sure the area around the tenon – the shoulder – is perfectly level.
P1110165
Checking that the flats (the planed/level part of the beam where braces will be attached) are at right angles to each other. You can see ink lines on the wood which are used for measurements.

 

An interesting aspect of carpentry is the use of inches rather than millimetres for measurements. Inches allow for easy subdivision – half, quarter, eighth, etc – are all useful and easily recognisable measurements to visualise rather than, say, 20 mils.

P1110145.JPG
Some of the beams receiving the finishing touch on the framing bed.

 

The Lay-Up

All parts of the timber frame are assembled beforehand on the framing bed, labelled and put to one side. These are then put together in the form of lay-ups (which is essentially a practice run where if there are any inaccuracies they can be corrected before the large beams are suspended in the air. Correcting at height will be more difficult and potentially dangerous, so time spent making adjustments on the ground is time well spent.

P1110180.JPG
Lay-up of the beams which form the henge for our twin reciprocal roof over the living room/kitchen

 

 

Concrete compromise

At the outset of our build we aimed not to use any concrete in its construction due to its large embodied energy and polluting production. Reducing the embodied energy in what we use is very important and this had led us to choose materials in their raw state so as to reduce our carbon footprint . However, we’ve had to compromise on this as our engineering specification for supporting the posts means we needed to use some concrete in order to achieve compliance and to ensure our house will be structurally sound.

We used 4 tons of concrete. I used an online calculator to calculate the amount we had to mix. Luckily our local hardware – Tullamore Hardware – allows returns of used bags of cement as it can be difficult to store on site.

P1110214.JPG
Reinforced concrete pads (17 altogether) with rebar. The rebar will ensure the posts can’t move from side to side, as they will be drilled to house the reinforcement.

 

We have enjoyed several visitors to our site in the last few months. It’s a great experience to share our ideas and dreams with friends and acquaintances.

 

Natural Building

There are many definitions and interpretations of natural building; it is a collection of different approaches to building rather than a ‘one size fits all’ term. One definition I think which adequately sums up our approach to natural building is “a building philosophy that emphasises sustainability through using minimally processed, locally available, plentiful and renewable resources to create healthy living environments” (Crimmell and Thomson, 2014). I think this is a much clearer definition than ‘green building’ or ‘eco-building’ – this three letter prefix has almost become meaningless when used in relation to the building industry and is often an example of ‘green-washing’.

In our experience when you reduce the embodied energy in your building materials, e.g. straw bales and roundwood you do have to add considerable amount of physical energy to the building process in order to utilise the materials. For example our roundwood had to be debarked and will have to be further cut and jointed to become structurally supportive – all of this takes lots of time and energy and no doubt the finish will be beautiful, but it is definitely not a short cut.

P1100915 (1)
To get most of the bark off we used both debarking spades and a small axe for tricky bits

The debarking of all our poles took four weeks (5/600 hours of labour) and involved brothers, sisters, nieces, nephews, fathers, uncles and friends. We had four debarking spades so that anyone who came could help out.

Luckily the weather in April was really dry so the moisture content in the wood has begun to reduce (some of the poles were over 50% moisture – they need to be below 20% when we close off the house).

It was great working outdoors during this period and we’ve been visited by a cock and hen pheasant, several rabbits, and, a startled hare. The cattle and the swallows have returned – along with other birds – there is a frenzy of nest-building in operation.

When completed we were left with a huge amount of bark which will be used as mulching around our site – for gardening and walkways.

The debarked poles were measured and marked with Roman numerals to aid identification in the construction phase – this task was quite complicated and took about two days to complete – we checked the lengths and diameters against our saw list and plans. The poles were then moved up to the site -we were able to move the small diameter poles (150mm) which will be used in the roof ourselves – but we had to hire machinery to move the larger diameter ones (300-350mm).

IMAG0797
Moving the large diameter poles

Unfortunately due to some humid weather mold has begun to grow on the poles, this is a natural occurrence on debarked wood, and we will have to deal with it when the poles are being erected in the timber frame.

The mold spores travel freely through the air and by debarking the poles we have provided an ideal habitat for them! We have experimented with bicarbonate of soda which not only removed the greenish/black mold but also seems to prevent it from returning.

IMG-20170510-WA0003
Large diameter poles on site. Next stage – wooden ring beam, frame and roof…

The next stage of our build is to begin work on the wooden ring beam which sits on top of the tyres and will support the straw bale walls. We will be working with a roundwood carpenter to help us with bracing the poles, and are awaiting the delivery of a tripod to aid lifting the large diameter poles.

IMAG0777
Marking each pole at both ends is essential. II means diameter 150mm and length 3,500mm (3.5m)

Our timing is quite important and ideally we’d like to have the roof on by the end of July/early August so that we can get the straw walls up and plastered before winter.

Harvesting the roundwood

IMG-20170401-WA0001
That’s a lot of wood and it all has to be de-barked too!

Using roundwood in construction is not widely practised in Ireland at the moment. Where roundwood is used it tends to be for small-scale structures. Its use for family homes is rare. This has led, in our experience, to a shortage of skilled roundwood carpenters and suppliers of specialist tools and other equipment. Hopefully in the future this situation will change, as people become more aware of roundwood’s natural beauty, strength and suitability as a building material.

Harvesting our roundwood was a detailed process.

Stage 1: The Saw List

This is a list of all the sizes and diameters of the wood which will form the post and beams for the walls and the rafters in the roof. Our saw list consisted of nearly 200 poles with 17 different lengths and four different diameters. Our engineer calculated the dimensions to meet specific building standards and to meet the design’s requirements for strength and load-bearing capacity.

Stage 2: Finding the forest

It was important for us to find a local, sustainable source for our wood. Ireland is one of the least afforested countries in Europe and we began the process of looking for our wood about six months beforehand, as we knew our lead-in time could be significant. I had spoken to another self-builder who used roundwood as part of the research for our home, which was vital in getting the timing right.

Our supplier was Paddy Purser (Purser Tarlton Russell Ltd) whose task it was to find a forest where all our wood could be harvested. This is more difficult than it sounds, as our wood would not be all the same age and therefor could not come from a forest which was clear felled. It had to come from a sustainably-managed forest, literally tree-by-tree.

IMG-20170210-WA0003
The forest in Clora, Co Wicklow

The forest was located in Clora, County Wicklow, and forms part of the mysteriously named, Devil’s Glen. The foresters then took our saw list and began looking for suitable trees within the forest. Individual trees had to be measured with a calipers. The forest adheres to ProSilva ideas and methods, which emphasises a tree-by-tree approach.

When the trees were identified they were then cut and transported to a collection point.

IMG-20170210-WA0002
Measuring the wood

We visited the forest to meet the foresters and to see where our wood came from. This was an important part of our building experience as we saw a very healthy forest environment and we made a connection with the origin of the main future supports of our home.

It was notable the much wider variety of wildlife in this forest compared to the dark, uniform forest plantations widely seen across Ireland.

Stage 3: Storing and debarking the roundwood

Storing all the wood on-site would have been difficult and luckily we were able to use the farm’s old silage pit, where the roundwood could be spread out, dry and be debarked. Storage of this amount of roundwood could be problematic on some sites, so it does need careful consideration.

P1100822
Debarking in the morning
P1100826
Debarking in the evening

Roundwood needs to be debarked as soon as possible after harvesting. Debarking removes the bark which is alive and moist, and a home for a variety of insects which can, if left un-debarked, slowly begin to eat your wood. We purchased several debarking spades for the Woodsmith website (I couldn’t find a supplier in Ireland).

Beginning the debarking process was pretty daunting! it was one of those moments when we thought “what have we let ourselves in for?” We have allowed ourselves a month to complete the task (working 5 and a half days a week). Log-by-log is the only way to proceed. Interestingly after delivering our wood, the driver was delivering his next load to the set of the Vikings for one of their sets.

Natural building methods can only be fully realised when you take your time and flow with the rhythm of your materials and tasks.

Spring planting and Living roof

In between ramming car-tyres with shingle and our wood arriving we’ve taken a few days to complete some gardening projects. One of our main priorities was to plant a shelter belt. Our site is exposed to south-westerly winds in particular, which is the predominant wind direction in Ireland.

Shelter Belt

Video 1 (146)
Some of the 100 bare root trees which was planted for the shelter belt.

We wanted to include a mixture of native trees and shrubs so that it would look more like a typical country ditch rather than a homogeneous row of equally spaced trees. We purchased 100 bare root trees from Premier Nurseries, they included; Beech, Rowan, Laurel, Chestnut, Hornbeam, Birch, and Alder. In addition we also planted some Oak, Ash, Willow which we were growing in pots. Most of the trees were 40-60cm and at this height they don’t need support and will find it easier to establish a root system and become stable than 1-2m trees. We also purchased some shrubs from a local supplier Gardenshop.ie, including; Wild Rose, Elder, Hazel, Whitethorn, Blackthorn, Dogwood and Cherry.

When we finished planting the trees we added a 40cm x 40cm square of root barrier with a few shovelfuls of shingle or loose stones on top to allow the trees to outpace the grass and to maintain good moisture.

I found Mary Reynold’s book – The Garden Awakening: Designs To Nurture Our Land and Ourselves – and, Forest Gardening: Rediscovering Nature and Community in a Post-industrial Age by Robert Hart, both very useful reading in developing my thinking about planting and how to develop our garden.

Living Roof

Video 1 (162)
Adding clay to the living roof.

The Studio we built, which is being used as a shed at the moment, needed more clay on the living roof and to be planted with wildflowers. It also needed to be treated so that the beautiful Douglas Fir colours would be given new life.

We planted the roof with wildflower seeds which we saved from out own back garden during last Autumn. We also collected a variety of grass seeds from grass which is not commercially grown. During the summer the roof should be full of colours and attractive to wildlife, especially the bees.

The studio was treated with Osmo Oil – a vegetable oil based treatment for wood from Pat McDonnell. It gives a superb finish and revitalised the wood as well as helping to fully water proof the building.

Mulch Path and Mini Herb Garden

P1100789
Mini car-tyre herb garden

Adopting a permaculture approach we laid down a mulch path to prevent the top soil being worn away in the most walked-on places. We removed the grass and soil and used it to cover some of the ‘bald patches’ caused by excavations. We cut up the large ton sack the mulch cam in to act as a weed barrier.

For the mini herb garden, we filled several tyres with the clay we excavated for the foundation of the compost toilet. We used root barrier off-cuts and old sacks in the bottom to prevent grass and weeds growing (Growing in tyres for root crops has some critics but I think for a herb garden it doesn’t pose and issues). Car tyres are useful in preventing certain types of herbs, e.g. mint from colonising.

P1100736